The City of Canyon is developing its first Safe Streets and Roads for All (SS4A) Plan  to improve roadway safety. This Plan will serve as a strategic roadmap to reduce crashes, address priority safety concerns, and create a safer, more accessible transportation network for all users, whether walking, biking, or driving. Guided by data analysis and community input, the Plan will identify key safety projects, policy updates, and funding strategies that reflect Canyon’s values and goals.

Together, we’re building a future where everyone can move through our city safely and confidently.


Map It Safer!

Thank you to everyone who participated in our first public engagement! The interactive map survey received 479 comments from the community. The project team is now reviewing the feedback and performing analysis to summarize key themes and safety concerns. Stay tuned for the survey results and findings.


Timeline

  • Timeline item 1 - complete

    Phase 1 - Foundation: Crash Analysis and Community Kickoff (Summer 2025)

    Build the foundation of the plan through early data analysis and meaningful engagement:

    • Establish Vision Zero Advisory Board and project committees
    • Conduct five-year crash data analysis using TxDOT CRIS
    • Launch first round of public engagement, including interactive survey and mapping


    On September 25, we kicked off our work with the Vision Zero Board. You can view the presentation here: 0925 First Vision Zero Board Meeting

  • Timeline item 2 - complete

    Phase 2 - Focus: High Injury Network and Capital Project Identification (Summer & Fall 2025)

    Translate analysis and engagement into actionable priorities:

    • Develop a data-driven High Injury Network (HIN) for all modes and vulnerable users
    • Conduct case studies to inform best practices and context-sensitive solutions
    • Identify potential capital projects based on crash trends and community input

    Please click this link for the City of Canyon's High Injury Network: High Injury Network Map

  • Timeline item 3 - active

    Phase 3 - Prioritize: Project Prioritization and Stakeholder Alignment (Fall & Winter 2025)

    Narrow focus to the most impactful safety solutions:

    • Prioritize capital projects across short-, medium-, and long-term timeframes
    • Refine purpose, concept, and cost estimates for five key projects
    • Share refined recommendations with stakeholders and the public (Public Engagement Analysis Memo can be found here: Canyon SS4A Survey Analysis Memo)

    On December 4, we hosted our second Board Meeting. The presentation can be found here: 1203 Second Vision Zero Board Meeting

  • Timeline item 4 - incomplete

    Phase 4 - Framework: Policy and Plan Review (Winter 2025)

    Identify gaps and opportunities within the City’s existing frameworks:

    • Review City of Canyon’s policies, design standards, and planning documents
    • Recommend updates that align with Vision Zero and Complete Streets principles
    • Identify potential cross-section updates for the MPO’s Thoroughfare Plan
    • Continue targeted outreach and advisory board coordination
  • Timeline item 5 - incomplete

    Phase 5 - Final Plan: Safe Streets and Roads for All (Spring 2026)

    Deliver the completed Canyon SS4A Plan:

    • Summarize technical findings, community input, and project recommendations
    • Finalize Capital Project Program List
    • Develop a funding strategy and matrix for grant readiness
    • Present the final SS4A Plan to City Council for adoption

Your participation in the planning process is welcome and needed. This website will contain information on each opportunity for you to participate in the planning process.If you have any questions about the safety planning process, please contact Yige “Eagle” Tang via ytang@thegoodmancorp.com or (713) 951-7951.